Why data center demand is showing up in household power bills
One grid operator covers 13 states and Washington, about 67 million people. Its own market monitor has put a number on what the data centers added.
About $16 a month. That is what Maryland’s Office of People’s Counsel estimated one auction result would add to a residential BGE bill.
It put the same increase at about $18 in the Potomac Edison zone and about $14 at Pepco.
Read those carefully. They are estimates, not billed totals. They cover an increase that began in June 2025. And they apply to residential customers in those Maryland zones only.
Who else is exposed to the same mechanism. Anyone on the PJM grid.
PJM Interconnection runs the power grid for 13 states and Washington. That is Virginia to Illinois, New Jersey to Ohio. About 67 million people live inside it.
Once a year it runs something called a capacity auction. Capacity is not electricity.
It is a payment to power plants for promising to be available on the day demand peaks. Customers pay it whether or not the plant ever runs.
It reaches a household through the supply part of the bill, not the usage part.
PAID PARTNERSHIP
Dear Friend,
Why would the world’s richest man buy a dead power plant?
A few months ago, with no press release, xAI bought the site of a shuttered Duke Energy plant in Southaven, Mississippi.
It made no headlines. But it tells you everything.
Musk’s supercomputer runs on temporary turbines that a federal permit shuts off on January 2.
He can’t wait the 3-to-5 years a normal power build takes.
So he’s seizing dead infrastructure and racing to power it permanently.
Now.
What it means for you: he needs the equipment, and the one company that can deliver it fast.
A small, publicly traded supplier fits exactly, still priced like nobody noticed the purchase.
“The Buck Stops Here,”
Kelly Maguire
Behind the Markets
© 2026 Behind the Markets. 4260 NW 1st Avenue, Suite #55 · Boca Raton, FL 33431. LEGAL DISCLAIMER: Personal results may vary. All investing involves risk of loss. Past performance is not a guarantee of future results. The information provided is for educational purposes only and does not constitute a recommendation to buy or sell any specific security.
Now the prices, with a baseline first.
For the 2024 to 2025 delivery year, capacity cleared at $28.92 per megawatt day. Treat that as the comparison point. It is not one of the four auctions below.
For 2025 to 2026 it cleared at $269.92. For 2026 to 2027, $329.17. For 2027 to 2028, $333.44.
For 2028 to 2029 it cleared at $325, which was that year’s price cap. Lower than the year before, and still at the ceiling.
THE STAKES
SEALED
$29.4BN
OF $63.6 BILLION, FOUR AUCTIONS, 2025/26 TO 2028/29
→
The grade applies to that $29.4 billion, which is contracted. It does not say your whole bill can never fall again.
That figure comes from Monitoring Analytics, the independent market monitor PJM pays to watch its own market.
Its estimate is that data center demand accounts for $29.4 billion of the $63.6 billion in capacity costs across those four auctions.
The monitor describes that increase as irreversible. The word covers money already committed in auctions that have closed.
It is not a forecast that electricity prices can only rise from here.
Demand is not easing. Amazon’s Andy Jassy says AWS capacity is sold out for this year and largely booked for 2027.
He adds that a good chunk of 2028 is gone too.
There has been an attempt to change who pays. PJM filed a plan aimed at very large new electricity users, which it defines as 50 megawatts and above.
They would have had to bring their own new generation, or be first in line to be cut off in an emergency.
On October 9 the Federal Energy Regulatory Commission rejected most of that plan.
Two pieces survived and took effect on October 12. The 50 megawatt definition, and a registry listing those users. Neither changes who pays.
PJM is expected to file a revised version of a separate plan around October 29. A follow up filing on the rejected one is due in early November.
On October 7 the Energy Department asked that the cost of serving new large users not be unfairly shifted onto existing customers.
Separate what is settled from what is not.
Those four auctions have cleared. The prices are set and the capacity is contracted. Nothing filed this month reaches them.
FROM OUR PARTNERS
Every machine we’ve ever built needed a person.
The tractor needed a driver. The factory robot needed an operator. The computer needed someone at the keyboard. Technology replaced muscle, then it replaced repetition, but it always left the thinking to us.
For the first time, we’ve built a machine that does the thinking. It reads the contract. Writes the code. Answers the customer. Makes the judgment call.
Here’s the part that decides whether this is a disaster or the opportunity of your life: someone owns the engine.
Every shift this big splits the world in two. On one side, the people the technology replaces. On the other, the small group who own the thing doing the replacing.
That gap has built some of the largest fortunes in American history.
The names to own. The names to sell. The three moves to put your family on the right side of the machine.
Good investing,
Porter Stansberry
What is being argued now is the rules for auctions that have not happened.
We are not going to name the delivery year an October filing would reach. PJM has been compressing its auction calendar, and the 2028 to 2029 auction already ran this July.
Three honest limits before the move. Capacity is one line on a bill, not the bill.
Retail rates are set by state regulators, so the same auction lands differently in Ohio than in Virginia.
And fuel, transmission and weather move the same bill. A higher total on its own proves nothing about data centers.
ADVERTISEMENT
A data center can be finished months before it gets power. You can invest in American PowerGen, the Texas company getting power projects ready ahead of time, from $1,000. See how American PowerGen gets projects ready.
Securities are being offered pursuant to Regulation Crowdfunding through DealMaker Securities LLC. Please review the offering materials, including the Form C, before investing at invest.americanpowergen.com.
EVERY LEAD PASSES BEFORE IT RUNS
The One-Way-Door Test
01
Can it be undone?
Not the four auctions that have cleared. The market monitor calls that $29.4 billion irreversible.
CLEARED
02
Who is already repositioning?
PJM. A revised filing is expected around October 29, covering auctions that have not been held.
OCT 29
03
What does being late cost?
Nothing on the bills already priced. The open question is the auctions still ahead of us.
STILL OPEN
THE MOVE · TEN MINUTES, ONE NUMBER
Put this October’s bill next to last October’s. The same month both times. Then compare the supply or generation charges, not the total.
Many bills show no separate capacity line. If yours does not, call the number printed on it and ask where capacity costs sit in your supply charge. That is the question that gets a useful answer.
A bigger total does not prove data centers caused it. Fuel, transmission and weather move the same bill. The supply charge is the only place the auction shows up.
ALSO GOT LOOSE TODAY
 
Trump signed an executive order on October 22 directing agencies to cut mortgage insurance and refinance costs. Freddie Mac had the 30 year fixed at 7.32 percent that week.
HOUSING
 
Moody’s held France’s credit rating steady as the country’s debt turmoil kept hitting markets.
WORLD
 
The Nasdaq fell 2.60 percent on Thursday to 26,009. Gold ended the week near $4,041 an ounce.
MONEY
WHAT’S LEFT AT THE BOTTOM
You cannot vote on a capacity auction. You can read your own supply charge, and after ten minutes you will know what the last four did to it.
WE WATCH THE BOX.